So that the building, and surrounding parking areas, could continue to be used by council staff during the course of the project, the programme was undertaken over 3 phases.

Works included demolitions, M&E, alarm and door entry systems, emergency call points, ceilings, lighting, data, power, power poles, structural openings, new partitions, demolitions, joinery, flooring, decorations

Flexibility was key on this project, as additional works were added during the programme. However, we were able to accelerate the project in its early phases to maintain the completion date.